CH 13 · Part B: Doing a real tender properly
Every warning on a drawing in TrueQty, and what to do about it
A flag is TrueQty saying: look here. This is every warning it raises, what each one found, which ones block approval, and what to do about it.
- Who can do this
- JuniorTeam leadAdmin
- Read first
- Video
- 3:45below the steps
In this guide
- 01Amber: look here
- 02Red: it blocks approval
- 03Green: it agrees
- 04Which ones block approval
How to read a flag
A flag means TrueQty may be wrong, or the drawing may be. Most flags never stop you working. A few block approval, and they are marked below.
- Amber means look here. You can still approve.
- Red means it blocks approval.
- Green means it checked, and they agree.
Every flag says, in plain English, what it found and what to do. Read it, look at the drawing, decide. The notices sit in one area above the drawing, and the notes about a device type show next to that type in the left panel, such as 1 note to read.
On the counts
| Flag | What it found | What to do |
|---|---|---|
| The drawing's own total | The count is close to, or far from, the total the drawing prints | Find the missing or extra devices. Warns, does not block. See The count check |
| Named but not drawn | A label names a device that has no symbol | Find the label, and add the device by hand |
| Different from the other floors | One floor has none of a device the comparable floors have, such as no door contacts where the others have about twelve | Look at that floor: truly none, or missed? |
| An empty patch | No devices in one part of the plan, while the area around it is full | Zoom in and look |
| A label or symbol on its own | A camera with no tag, where most others on the drawing have both | Check it is a real device |
| The odd one out | A single shape much larger than every other device | It may be a camera's coverage wedge, not a camera. Look before you count it |
| A checked device has gone | After the drawing is read again, a device somebody had checked is not on the drawing any more | Check that device type again |
| Two totals on one drawing | The drawing's own figures disagree with each other | Neither is used. Decide which is right, and ask |
On the drawing
| Flag | What it found | What to do |
|---|---|---|
| Read, and no devices found | The drawing was read and nothing on it matched a device | On a location plan that can be right. On a floor plan, treat the count as unknown, not zero. Blocks approval until something is counted |
| Reference only | The drawing is a schematic or riser. Its devices are counted on the floor layouts, so nothing on it is counted | Nothing, if it is a riser. If it is a floor layout, click Count it as a floor layout |
| A device type counting zero | A device type counts zero with a note against it. A zero with no device prices as free | Blocks approval until somebody looks |
| No scale stated | The drawing states no scale, so its cable lengths use the project scale | Read the ratio off the drawing, and enter it in Drawing details |
| Door hardware | A door with a contact but no lock, a lock but no contact, or a second lock almost on top of another | Check the door. A second device almost on top of another is likely one device counted twice |
| A DWG or DXF file | It cannot be shown for checking, so its counts cannot be approved, and they stay out of the BOQ | Open it. Upload a PDF exported from CAD is recommended and the most accurate. Convert it to PDF here is quicker, but conversion can lose detail, so check every count on a converted sheet carefully. Either way the PDF becomes the counted copy. See Which files work best |
| Not ready to approve | The checklist above Approve counts: device types still to check, nothing counted, device types counting zero | Blocks approval. Clear each line |
On the system, cabling and pricing
| Flag | What it found | What to do |
|---|---|---|
| More devices than ports | More devices are routed to a rack than it has ports, such as 73 devices on 72 ports | The plans and the riser disagree. Raise it with the consultant, or add a switch |
| A run over the limit | A whole cable run longer than the project's limit, such as 90 m for copper | It needs a nearer rack, or a re-route. Flagged for review, never priced quietly |
| No network rule | A device type with no network rule adds no cable and no switch ports | If it connects to the network, contact Help and support |
| Pricing gaps | Lines showing No price, and a Total of priced lines that leaves them out | Get a quote, or type a rate by hand |
Watch it done
Open on YouTubeThe same steps, on the sample tender, in 3:45.