How to make the BOQ from your drawings
Turn the approved counts into a BOQ: a line for each device type on each floor, then everything those devices need, from cable to switches.
- Who can do this
- JuniorTeam leadProcurementAdmin
- Read first
- Video
- 1:07below the steps
In this guide
- 01From the approved counts
- 02One line per type, per floor
- 03Everything the devices need
- 04Ready to price
Before you start
Every floor layout in the project has to be approved first. That is a team lead's job: see Approve a drawing's counts. The BOQ takes counts only from drawings that are approved, can be shown here and have been checked. Risers and schematics are kept as reference and never go in the BOQ, and nor does a CAD file that cannot be shown: the PDF of it does.
Step by step
- On the project page, click Make the BOQ in the next step at the top. It appears once every drawing is approved. BOQ and prices, in the steps at the top, opens the same page. Until then the page says BOQ is waiting for approvals and lists each drawing still to approve, one click away.
- Read BOQ by floor. The page always opens on this tab, and it shows the approved counts floor by floor even before there is a BOQ. See Reading BOQ by floor below.
- The first time, open BOQ lines and click Make the BOQ, then Make the BOQ again in the box that asks. It makes the first BOQ from the approved counts.
- Open All lines and read the BOQ from the top. The lines are grouped by system, each with its subtotal:
- Devices: one line for each type of device on each floor, such as cameras, card readers, door contacts and locks.
- What the devices need: the cable, the patch panels and cable organisers, the cabinets and the switches.
- See where a quantity came from. A line made with its workings has How this was worked out under its description. Where the riser shows a piece of equipment, and its rack has been checked, the BOQ takes it from the riser. Where the cable schedule gives the lengths, the BOQ takes them from there, and says so under Cable lengths. See The riser and the system view.
- Open Rules used to see every rule this version was made with.
Check it worked
You have a BOQ with its lines listed, marked Version 1. On the sample tender it has 27 lines.
Reading BOQ by floor
BOQ by floor lays the approved counts out the way a main contractor's ELV BOQ is laid out:
- A tab for each system, such as CCTV and ACS, with its total beside the name.
- Floors down the side, in building order. Where a confirmed riser names the IDF serving a floor, it shows under IDF REF.
- Device types across the top, in the wording a contractor's BOQ uses, such as DOME CEILING MOUNTED CAMERA, split into its classes: ID, REC., OBS., DET. and MON.
- TOTAL at the foot of every column.
A 0 means none on that floor, approved. A - means a drawing for that floor is not approved yet, so the number is not known. Click any count to see Where this number came from: the drawings it was counted on, each opening with only those device types shown. Below the table, Drawings in these counts lists every approved drawing, who approved it and when. A typical floor drawing is counted once for each floor it stands for.
On this tab, Export to Excel downloads BOQ by floor as a workbook: a sheet for each system, a TOTAL row that adds up again in Excel when you change a count, and a last sheet listing the drawings every count came from. On a project split into packages, each package's BOQ by floor holds its own drawings only.
A read-only seat
A read-only seat can open the BOQ and export it, but cannot make, change or issue it. The page says so at the top.
Next
Price the BOQ from your vendors' quotes or price lists, and add your markup. To understand every line in depth, see The BOQ formulas.
Watch it done
Open on YouTubeThe same steps, on the sample tender, in 1:07.
Finished this guide?
Mark it done to track your way through the Academy.