The cable schedule: run lengths and the 90 m check

Read a cable schedule line by line: every device's run, with the working beside it, the 90 m copper check, and the cable to order in whole boxes.

Who can do this
JuniorTeam leadAdmin

In this guide

  1. 01Every run, with its working
  2. 02Measured or estimated
  3. 03The 90 m check
  4. 04Boxes to order

Once the riser is in, TrueQty builds a cable schedule: one row for every device, with its tag, its floor, its rack, its cable and its length.

Step by step

  1. On the project page, open the Racks and cables tab, and find Cable schedule. It says how many devices are routed, such as 213 of 213 devices routed, and how many are awaiting a rack. If some are, the next step on the project page says so too.
  2. Click Show the 213 device rows (the button shows the count).
  3. Read the Build-up column. Each length shows its working:
    • the route on the plan, in metres, at the drawing's scale,
    • times a routing factor, for trays and bends,
    • plus the drop from the ceiling to the device,
    • plus slack at the device, and more at the rack,
    • equals the run, in Length (m).
  4. Read How it was worked out.
    • measured: it measured to the rack's position on the plan.
    • estimated by average: the rack is not drawn on the plan, so it used the floor's average run. The line above the rows counts how many of each.
  5. Look for red. Any whole run over the project's limit, 90 m for copper unless you change it, is marked in red on its row and counted above the rows. It is flagged for review, never priced quietly.
  6. Read Horizontal cable to order, at the bottom. Every run added up for each cable type, 10% waste on top, rounded up to whole 305 m boxes, such as 27 boxes.
  7. Read Backbone riser below it, such as 3 links and 54 m between floors: per rack, the floors to the head end, the rise, the slack at each end and the total.
  8. Click Export schedule to get all of it in Excel, with the working beside every number. A device with no rack is included, with its reason.

The formula

Run = route on plan × routing factor + drop + slack at the device + slack at the rack

The values behind it are the project's cable standard, just above the schedule, and you can change them: see The cable standard.

If a run is over 90 m

The device needs a nearer rack, or a re-route. Raise it with the consultant. TrueQty flags it and does not price it as if it were fine.

Watch it done

Open on YouTube

The same steps, on the sample tender, in 1:39.

TrueQty Academy/CH 17/The cable schedule

Finished this guide?

Mark it done to track your way through the Academy.

Follow along on your own tender. Every guide works the same on a real drawing.

Start free trial